If it does not drop, but there is slow leakage at test cock No. 3, then No. 1 ball valve has a small leak, but No. 2 check valve is tight.
如果水柱没有下降,但是测试旋塞3号有点泄漏,则1号球阀有点泄漏,但是2号止回阀密封紧密。
Open test cock No. When flow of water out of test cock No. 2 stops, the differential reading is the pressure drop reading.
开启测试旋塞2号。当从测试旋塞2号流出的水流停止时,压差读数就是压降读数。
Connect bypass hose between connection "C" bypass and loosely to test cock No.
将旁路软管连接到连接「C」旁路并松散地连接到测试旋塞1号上。
Install hose between test cock and connection "A" high side (red) of test kit.
在测试旋塞和检测组件的连接「A」高端(红)之间安装软管。
The shutoff valve with the test cock is to be mounted on the inlet side of the backflow preventer.
带测试旋塞的关闭阀应该安装在防回流阀的进口侧。
Open test cock No. 1 and bleed valve by opening vent needle valve. Bleed air from hose then shut vent needle valve.
开启测试旋塞1号,通过开启排气针形阀来开启排气阀。从软管排放空气,然后关闭排气针形阀。
The gate valve with the test cock is to mounted on the inlet side of the backflow preventer .
带有测试旋塞的闸阀安装在防回流阀的进口一侧。
Requirement: Supply pressure drop must be 0 PSID or more when water flow stops from test cock No.
要求:当水流从测试旋塞2号上停止时,供应压降必须在0PSID及以上。
If it slowly drops and simultaneously runs out through test cock No. 3, check valve No. 2 is leaking and must be serviced.
如果水柱慢慢下降,并且同时通过测试旋塞3号排出,则止回阀2号泄漏,必须维修。